Home About Me Excel VB Programming (97-2003) Excel Spreadsheet Formulas Excel VB.NET Programming Access Programming (2000-2003) Material Management
Demand Forecasting |
Reorder Point Technique and Safety Stock MRP in the your ERP computer systems accommodates all order trigger methods and review techniques. Reorder Point is one the order methods used. The risk of not using Reorder Point n your inventory control is that your available stock balance will dip into safety stock level or a stock-out will occur before an order is even released during your next review period. Planners have a choice of two types of Reorder Point trigger techniques which are logic controlled within most of today’s computerized systems – quantity-based or demand-based reorder triggers. Quantity-based reorder Demand-based reorder If the reorder review occurs too early, average inventory levels may exceed the target as stock are replenished far earlier than the actual date of the projected stock-out or before safety is dipped into. If the reorder review occurs too late, a shortage may occur and additional costs may be incurred to expedite the needed parts. Parts using a lot-for-lot dependent demand order are never reviewed using reorder point but are only ordered as each individual demand occurred. Lot-for-lot order quantity is generated automatically as part of the MRP explosion process. Parts without target safety stock and MRO inventory items do not need reorder point. Planners must give special attention to the overall “Time-to-receive” for parts using reorder levels – this includes order review and order release time, supplier lead time, transportation time, custom clearance, receiving, inspection and storage time. Base on the knowledge the planners have on the parts, supplier performance and business conditions, they will adjust reorder levels necessarily, change review cycle or order methods.
Types of control with reorder trigger The planners use different planning methods for order review triggers, base upon the types of parts stocked for manufacturing, after-sale service and operating support; types of parts procured externally or manufactured on-demand, and the company’s computer system logic used. Most companies today use MRP triggers but some use a combination of MRP and inventory reorder triggers. Three different part categories determine the type of control that planner should apply: master-schedule planned parts, MRP-planned parts, and inventory-planned parts (figure 3.1).
Figure 3.1 Master Production Schedule explosion and demand types Master-schedule
planned parts MRP-planned parts Planners sometimes decrease the assembly order quantity in a work order booked for certain customers, change its due date that will affect the quantity and timing of the lower and upper level demands. MRP systems are capable of online recalculation and planner can immediately see the effect of the change. However, the planner should analyze the effect before committing the change especially when changing the promise date is affecting a customer who is already very unhappy with the company’s poor service level performance or is a strategic customer. Inventory-planned
parts
Reorder Point Technique ROP technique is used for inexpensive independent-demand, and sometimes high volume usage parts where sufficient safety stock can be maintained to minimize risk of a stock-out. The concept of ROP is that order must be placed with the supplier at the point where there will be enough time to receive the material by the time the stock on-hand balance reaches the safety stock level. ROP assumes that the safety stock will never be dipped into but practically it often is not true. Below is the ROP formula. It is better to use forecasted daily usage rate than forecasted monthly usage rate because the number of workdays is not consistent every month. ROP = [(Forecasted daily usage x Lead time in days) + Safety stock]
Figure 3.2 Three review conditions of a Reorder Point technique Figure 3.2 shows three reorder review conditions that are faced by the planners – actual usage rate equal to, less than, or greater than forecasted usage rate. In the first case, actual usage rate may match the forecast, and generally this means that you are right on target with your inventory level as you planned. In the second case, actual demand may exceed the forecasted usage rate. If such higher usage rate continues, safety stock will be consumed and the part will stock-out before the released order is received into warehouse. You will have a lower average inventory level than targeted. The planner must have good knowledge of the part type, part family and its demand profile to determine whether the actual high usage rate will continue to be higher than forecast or whether it will average out to the forecast over time. If the planner judged that the actual demand will continue to be higher and safety stock won’t be enough to prevent the part from stock-out, the planner will expedite open orders and flag the part for next reorder level review. Of course the 3rd case, if the actual demand is lower than the forecasted usage rate, you have a higher than average inventory level and lower turns. Let’s see this example.
This means that this part will be expected to have stock-out if the current usage rate of 4 per day continues. This is because safety stock will only cover against a quantity 2 of forecasted daily usage rate. At current daily usage rate of 4, the ROP is revised to 65 instead of forecasted 37.
Time-Phased Order Point Technique This type of order review technique is used extensively by purchasers/material planners in MRP system and in Central Distribution Center (CDC) system. CDC receives orders from regional warehouses (dependent-demand using Inter-Company Order or sometimes called Transfer Order) and also directly from customers (independent-demand). The logic is embedded in your company’s MRP system but I want to give you a refresher here with an example below.
In the above table, the weekly dependent demand comes from requirements determined as a result of higher level bill of material exploded by MRP system. The constant independent demand comes from forecast calculated from historical usage. You can download this worksheet with the formula. There are 60 pc available in the current period (beginning inventory 80 - safety stock 20). 140 pc based on fixed-order qty are scheduled to be received in week 11, the week after next. If 140 pc scheduled receipt in week 11 did not happen, there will not enough projected on-hand to meet the gross requirement 40 pc in week 12. Hence the negative net requirement of 8 pc. Now look at week 14, the gross requirement of 52 pc can not be satisfied by its beginning stock balance of 41 pc. This gives the net requirement of 11 pc (52-41) but fortunately you still have the safety stock 20 pc to meet the shortfall of 11 pc. Since there is no open order scheduled for receipt in week 14 and none in the weeks after that you can possibly expedite, the system will know that an order need to be released. Embedded logic in your system will calculate backward 21 days from week 14 to determine the exact date when the order must be released - it will be a date week 11. Assuming this released order is received as scheduled, 129 pc will be the projected inventory for week 15. The planner will extend the weekly demand and ordering profile to the end of the planning horizon.
Next Page >>
More on Safety Stock techniques...
|