Home About Me Guestbook Excel VB Programming (97-2003) Excel Spreadsheet Formulas Excel VB.NET Programming Access Programming (2000-2003) Material Management |
ROUGH CUT CAPACITY PLANNING The main reason why Rough Cut Capacity Planning (RCCP) is needed because Material Requirements Planning system (MRP) assumes that needed capacity always is available. RCCP helps to identify the key resources (material and personnel shortages, lead time constraints, capacity issues, sole supplier, space, machineries, process bottlenecks that limit output), and to test the feasibility of the supply plan, production plan and master schedule before doing any detailed capacity/material planning. It also helps to initiate action for making mid- to long-term capacity adjustments. (Supply Plan can include purchased parts whereas Production Plan is strictly for production). In this section, I will show you the RCCP technique using Resource Profile approach. I will not go through other RCCP techniques like the Overall Factors (CPOF) and the Bill Of Labor (BOL) approach, which are least detailed, implicitly assume a Lot-For-Lot policy for setting lot sizes, and are also insensitive to the shifts in product mix. They also do not take Lead-Time Offset into account, but which the Resource Profile approach does. In any event, rough-cut capacity plans should be used only to determine if sufficient capacity exists over broad time frames such as a month or a quarter.
A problem commonly encountered in operating MRP systems is the existence of an Overstated MPS. An overstated master production schedule is one that orders more production to be released than production can complete. An overstated MPS causes raw materials and WIP inventories to increase because more materials are purchased and released to the production floor than they can be completed and shipped before due dates. It also causes a buildup of job queues on the shop floor. Since jobs have to wait to be processed, actual lead times increase, causing ship dates to be missed. As lead times increase, forecast accuracy over the lead-time diminishes because forecasts are more accurate for shorter periods than for longer ones. Thus, an overstated master schedule leads to past-due orders and other problems. Validating the MPS with respect to capacity is an extremely important step in MRP, and is called Rough Cut Capacity Planning. There is no hard and fast rule on the level of detail that should be incorporated in the MPS validation. Some companies used very crude techniques, other used detailed, time-phased, methods.
In MRP system, the functions of capacity planning and control are separated from the functions of priority planning and control. Priority planning is the task of the MRP system. Priority control is determined, for instance, on the shop floor by the use of a dispatching technique to sequence specific tasks on specific machines. A few reasons I can think of why RCCP techniques are not used in some companies are: (1) data requirements are quite high - firm demand, forecasts, past data, lead times, utilization, products and process knowledge. (2) they don't have a stable MPS. If forecast and firm orders keep changing within week, and people bypassing agreed DTF and Planning Time Fence, capacity planning is a futile exercise. (3) they don't have the right skill, it is very time-consuming, or they are doing it the wrong ways. All companies running MRP should implement capacity planning. Companies that have unstable master schedules can also be due to inadequate Safety Stock at the MPS level (besides orders and forecasts push in and push out, human errors, etc). The inadequate safety stock can be due to a poor demand forecasting or failure to measure Forecast Error. In turn, safety-stock level can provide protection against forecast error. For capacity planning process to be effective, we must make sure that there is adequate safety stock level, improving forecast error, and a stable master schedule (as I said, frequent last minute schedule changes are very expensive).
When using process routings sheet and BOM to create the Resource Profile, it is better to use this formula:
We also need to determine Lead-Time Offset, which is the time between the need for the resource and the date that the product has been promised. Lead-Time Offset is necessary if a product has longer lead times. Figure 16.6 illustrates a time line of the resources identified through the process routing for the critical Base Assembly. It shows that the longest lead time needed for the base assembly is 28.45 days, so the lead-time offset for this resource is about 29 hours prior to the completion of the lamp assembly. Every resource has its lead-time offset, but practically if the offset is less than 30days, you don't need to consider it when evaluating the validity of the production plan. In this case, even if you rough-cut master schedule and plan production on weekly basis, 29 hours is well within one week. Now, with the key resources profile ready at hand, Johor Lamps want to validate the master schedule for the next 6 months, to verify whether there is adequate capacity at all key resources to meet the production plan (Figure 16.7). Of course, assuming there's a stable MPS. The technique involves comparing a machine-load report of required capacity to planned-available capacity at each work center. Here we need to understand there are several types of capacities being used. Demonstrated Capacity Planned Capacity Maximum Capacity Determining Capacity
Available or Planned Capacity Capacity available is determined by multiplying time available x utilization x efficiency:
The Resource Profile Technique Resource Profile technique uses detailed data on the time
standards for each product at the key resources. A Time Standard
is the time it should take an average worker working at a normal pace to
produce one unit of an item. The time standard for any part has built
into it an allowance for rest to overcome fatigue or unavoidable delays,
etc. Because production processes are continually improved, time
standards become less reliable unless they are being updated. For this
reason, you should not use time standard that is two or three years old
to perform capacity study. However, poor standards are not an absolute
barrier to capacity planning; you can use an adjustment factor known as
“efficiency” to correct for outdated time standards (although
efficiency is not intended to reduce the need to keep time standards
updated). The detailed Resource Profile approach also requires standard
times data, and additionally, lead times required to perform certain
tasks. The results of RCCP using the Resource Profile approach for Johor
Lamps can be developed as this example shown in Figure 16.7 below. The
computations are in the worksheet available for
download. At one glance in Figure 16.7,
you can see that there are Overloads at Chemical Dip and also for
supplier XYZ in the same month of Nov, Dec and Jan. The Required
Capacity in the these 3 months exceed the Planned Capacity as indicated
by the negative Net Variance (in red fonts). The same situation happens
for supplier XYZ. The projected Underloads are especially serious
throughout the six months in Copper-Plating, Final Assembly Line 1 & 2,
ranging from 40% to 78%. If you look at the total % variance for these
three key resources, there are projected schedule overloads of 47% in
Copper-Plating facility, 61% in Final Assy Line 1, and 70% in Final Assy
Line 2. Note that the Planned Capacity has already included the Maximum 10%
overtime that is permitted.
This graph on the left is plotted on
Now, what can you do about the rest of production planning after reviewing the results from this rough-cut capacity analysis over the 6 months period? Well, before making any changes or take actions, you need to do another rough-cut analysis, this time at the master schedule level. Companies that have varied mixes of products are especially compelled to do this. RCCP at the master schedule level use the same logic as rough cut at the production plan level, only difference is the calculations are extended down one or two additional levels. The master schedule is "exploded" through the Resource Profile to generate the required capacity to meet the master plan. Let's look at one month, Nov, to analyze projected capacities on a weekly basis, at the Overload resource - Chemical Dip. Figure 16.8 shows the quantities scheduled for each master schedule item. Note that the totals are the same as in Figure 16.4 Nov's totals, but clearly this 2nd-phase MPS rough-cut yields more detailed information, since it is at the component items level. The difference here is that the product families volume are broken down into component totals for the month, and analyzed on a week-by-week basis. To do this, take the quantities for each master scheduled item, multiply by the time requirements in the resource profile. (you need a SUMPRODUCT formula). All formula are in the worksheet for download. These component items are from the forecast, firm planned orders, and booked orders.
Of course, in other industries and different environments, these guidelines may need tighter tolerances, say, 5% to 10%. Implement necessarily as you can deem fit. For November, week 43, 44 & 45 in Figure 16.8 have revealed serious overloads even though the planned capacity has already included the max 10% overtime allowed. What causes it and what can be done? It might be possible to assign the workers from Final Assembly 2 Lines where underloads are projected, to help in the Chemical Dip department for the first 4 weeks in Nov. Splitting lots might helps to reduce some waiting time. It also might be possible to shift some of the volume from Nov 1st week to Oct where there is a little excess capacity. Of course, any decision of moving in or shifting out a master scheduled item requires consideration of the impact of that move on the ability to meet the customer promise dates. As a last resort, you can either tap into the maximum capacity which has included the 4 weekends, or sub-contracting out some of the load to approved vendors. Using the same calculations and analysis, you can extend to cover the rest of the key resources to have detailed view of all the MPS items and take appropriate corrective actions. In many of today's ERP systems, there is also a "What-If" scenarios analysis capability being built into the capacity planning module, that makes it possible for the scheduler to juggle the numbers - shifting workers, reschedule in and -out, alternate routings, splitting lots, add equipments, off-loading to vendors, overtime, hiring temporary workers and so on. Revising the
Master Schedule If de-expediting, overtime, subcontracting, alternate routing, and shifting personnel collectively cannot provide sufficient capacity, MPS revision does in fact become the technique of last resort, It is important to understand that when an unavoidable capacity overload exists, it must be corrected. If insufficient capacity exists, it is impossible to complete all orders on time. The choice now is to have management decide whose order will be late based on the impact on the whole business. Next Page >>
Detailed
Capacity Requirements Planning |
This site was created in Feb.2007 |